Manufacturing

Automation revamping tire handling system

Before cure tire handling system - Manufacturing

Roanne (FRANCE)

Project environment:
Revamping of before Cure Tire handling systems
Services provided:
Site Survey
Automation and Electrical design
Modification of the 15 systems following customer’s programming standards (ControlLogix)
Simulation of the Tire handling systems
F.A.T.
Tests phase by week-end with roll back plan
Technical assistance, commissioning and operator training
Equipment implemented:
Replacement of 12 PB80/PB400 PLCs by 12 controlLogix PLCs
Hardwired Input/Output Quantity :1 200

Automation revamping tire manufacture

Before cure Tire handling system - Manufacturing

La Roche sur Yon (FRANCE)

Project environment:
Revamping of before Cure Tire handling systems
Services provided:
Site Survey
Modification of the 17 systems following customer’s programming standards (ControlLogix)
Simulation of the Tire handling systems
Tests phase by week-end with roll back plan
Technical assistance, commissioning and operator training
Equipment implemented:
Replacement of 10 PLC5 PLCs by 10 controlLogix PLCs
Hardwired Input/Output Quantity : 2 100

Transitic revamping for tire handling system

Before cure Tire handling system - Manufacturing

Homburg (GERMANY)

Project environment:
Revamping of before Cure Tire handling systems
Services provided:
Site Survey
Modification of the 18 systems following customer’s programming standards (PLC5, SLC500 and ControlLogix
Simulation of the Tire handling systems
Tests phase by week-end with roll back plan
Technical assistance, commissioning and operator training
Equipment implemented:
Replacement of 1 PLC5 PLC by 1 controlLogix PLCemplacement de 1 API PLC5 par 1 API ControlLogix
Hardwired Input/Output Quantity : 2 000

Revamping – Systems optimisation

Retrieval machine and palletising system - Manufacturing

Roanne (FRANCE)

Project environment:
Revamping of storage and retrieval machine and palletising system
Services provided:
Site Survey
Automation, electrical and mechanical design
Modification of the 5 systems following customer’s programming standards
Simulation of the systems
Manufacturing and F.A.T.
Technical assistance, commissioning and operator training
Electrical and mechanical work contract
Equipment implemented:
Replacement of 2 PLC5 PLCs by 2 controlLogix PLCs
Hardwired Input/Output Quantity : 350

Production

Biscuit factory - Manufacturing

Vervin (FRANCE)

Project environment:
Production manager, ingredients and recipes, batches launch and analysis
Services provided:
Design: Data base
Communication: Siemens PLC link
Historic: Ingredient package, recipes, batches
Report: by shift, by days
Delivery: Installation, configuration and training on site
Equipment implemented:
Rockwell: FTView and Transaction Manager
Microsoft: SQL Server 2012 R2, Report Service
KEP: KEP Server

Test Emulator – Level 2 Migration

Revamping - Manufacturing -

Aranda (SPAIN)

Project environment:
Industrial site renewal – Tyre industry
Test emulator for L2 migration
Services provided:
Study and implementation of a simulator
8 Systems / 18 Decision points
Routing and flow tests with 18 decision points
Connection to 8 Rockwell PLCs
PLC5 – SLC500 – CLX
(~ 1500 Inputs/Outputs)
Equipment implemented:
Plug’n Test®
3D VIA – Virtools
OPC Server RSLinx

Tire industry- Dedusting systems

Dedusting system - Tire plants

China - India - Brazil

Services provided:
Electrical, pneumatic and automation design
Drafting of procurement and erection specifications
Electrical Equipements manufacturing and FAT.
Technical assistance to customer, commissioning and operator training/ 8 months
Electrical sites erection works sub-contracting / 3 X 7 500 hours
Equipment implemented:
52 PLC cabinets/ MDPB (ROCKWELL COMPACTLOGIX, POINT I/O, HMI PANELVIEW 700)
60 Frequency converters (ROCKWELL POWERFLEX)
163 Pneumatic cubicles